Permission to Operate SOP

Use this SOP after the system passes inspection and the utility issues Permission to Operate.

The purpose of this stage is to document PTO, complete customer onboarding, confirm the system is energized and visible in Daylight’s Solar portal, and finish the project closeout requirements.

Step 1: Upload the PTO Approval Letter

Once PTO is received from the utility, upload the final approval letter in the PTO Approval Letter section.

The document must clearly show that the utility has approved the system to operate.

Do not upload:

  • An interconnection application

  • A submission confirmation

  • A meter-work notice

  • A document showing that PTO is still pending

Daylight will review the uploaded letter and approve or return it for correction.

Step 2: Send the Customer Onboarding Invite

Click Send Customer Invite.

This sends the customer an invitation to complete Daylight onboarding and configure their payment account.

The portal will show Customer Onboarding Completed once the customer finishes the required setup.

If onboarding remains incomplete, follow up with the customer before project closeout.

Step 3: Complete the ITC Commissioning Checklist

Complete the required commissioning checklist in the portal.

The system should be commissioned using Daylight’s connected Sol-Ark portal account whenever possible.

  • Commission the system using the Daylight installer login provided for commissioning.

  • Confirm the inverter and batteries appear online in the Solar portal.

  • Confirm production and equipment status are visible.

  • Make sure there are no blocking alarms, communication errors, or offline devices.

If the system was commissioned under another account, transfer or share the system with [email protected] so Daylight can verify system status and production.

The next closeout steps will remain locked until the checklist is completed and approved.

Step 4: Upload Proof of an Energized System

Once the commissioning checklist is approved, upload proof that the system is on and producing.

Acceptable proof includes:

  • A photo showing the inverter in the ON position

  • A photo of the inverter display showing solar production

  • A screenshot from the Solar portal showing the system online and producing

The proof must belong to the correct project and clearly show that the system is live.

Click Submit Photo for Review.

Step 5: Confirm Daylight Solar Portal Access

Daylight must be able to view the system in the connected Solar portal before final approval.

Confirm:

  • The correct customer and project are connected

  • The inverter and batteries are reporting

  • Solar production is visible

  • Equipment status is healthy

  • The system has been transferred or shared with [email protected], when required

If Daylight cannot see the system in the Solar portal, investigate the equipment and monitoring connection before contacting Daylight.

Missing access, offline equipment, or incomplete production reporting may delay final approval and payment.

Step 6: Generate and Sign the Final Completion Certificate

Once the required PTO and commissioning items are approved:

  1. Click Generate Certificate.

  2. Review the Final Completion Certificate.

  3. Complete the required signature process.

The certificate confirms that the project has been completed and is ready for final closeout.

Step 7: Generate and Sign the Release of Claims

Click Generate Release of Claims.

Review and sign the document through the portal’s signature workflow.

The Release of Claims must be completed before the certificate package can be submitted.

Step 8: Submit the Certificate Package

Before submitting, confirm:

  • PTO Approval Letter is uploaded and approved

  • Customer onboarding is complete

  • ITC Commissioning Checklist is complete

  • Daylight can view the system in the Solar portal

  • Proof of energized system is uploaded and approved

  • Final Completion Certificate is signed

  • Release of Claims is signed

Submit the completed certificate package for Daylight review.

If anything is incomplete, inaccurate, or belongs to the wrong project, the package will be returned for correction.

Step 9: Complete the Final Milestone Invoice

Once the certificate package is approved, the applicable final milestone invoice will become available for signature.

Complete and sign the invoice in the portal so it can move into payment processing.

Before You Submit

Confirm:

  • The PTO letter is the final utility approval

  • The customer has completed onboarding

  • The system is commissioned and producing

  • Daylight can see the system in the Solar portal

  • The inverter and batteries are online

  • Proof of production is clear and current

  • All closeout documents are signed

  • Every document belongs to the correct customer and project

Complete and accurate PTO documentation helps prevent project-closeout and final-payment delays.